Grid connection 20(35) kV


 

Building start:

Commissioning:

July 2011

Februar 2012

Locations: Villages Strgačina~Kopači, Municipalities Rudo~Novo Goražde
Investor: ERS d.o.o. male hidroelektrane
General data: Nominal voltage: 20(35) kV 
Over head line: approx. 12,5 km
Cable line: approx. 4 km

Providing electricity for:

Approx. 8.000 households

 

Contribution to the nature:

CO2 savings: 26.000 t/year